Chișinău Municipality continues to implement essential projects for a cleaner and more modern city. With the support of international partners, we are making significant investments to improve waste management infrastructure.
Project: Modernization of I.M. Regia „Autosalubritate”
Period: 2021-2025
Partners: EBRD, EIB
Achievements to Date:
Essential Equipment for Improving Public Services:
-
3,000 European-standard waste containers acquired for efficient waste collection
-
44 new specialized vehicles for modernizing the sanitation fleet:
-
8 IVECO tractor units
-
8 EFE semi-trailers
-
6 MAN specialized vehicles
-
30 RENAULT specialized vehicles
-
-
Developed a methodology for calculating tariffs for waste management services
Investments in Waste Collection and Processing Infrastructure:
In 2024, contracts were signed for strategic projects:
-
Construction of a modern waste transfer station with a sorting line
-
Rehabilitation of the waste landfill in Ciocana
We collaborate with top international companies to implement these projects:
-
GOL CEVRE TEKNOLOJILERI Ltd. (Turkey) – leader of the JV WATT-GOL consortium for landfill rehabilitation
-
LIV MUH MUS INS LTD. (Turkey) – responsible for technical supervision of the works
Investments by Year:
2022:
-
€298.4 thousand – maintenance of the Project Implementation Unit
2023:
-
€1,448.0 thousand – acquisition of waste containers
-
€1,424.7 thousand – acquisition of MAN and IVECO specialized vehicles
2024:
-
€500.0 thousand – acquisition of RENAULT specialized vehicles
06-07.2024:
-
€3,092.0 thousand – acquisition of additional RENAULT specialized vehicles
-
€1,424.7 thousand – acquisition of MAN and IVECO specialized vehicles
Total investments made so far: €7.21 million
Ongoing Works in 2025:
Rehabilitation of the Ciocana landfill and construction of the transfer station:
-
A new access road to the construction site has been built
-
The site has been prepared, and modular containers have been installed for site organization
-
Temporary connection to the electrical grid has been completed
-
Next steps: final design and connection to water and sewage networks
What’s Next?
-
We continue investments in modernizing and optimizing the waste management system
-
The work on the transfer station and landfill rehabilitation in Ciocana is progressing as planned
-
International partnerships help us implement the best practices in the field
Together, we are building a cleaner and more modern Chișinău!